Question 1
A line operates with Availability 90%, Performance 95%, Quality 99%. The OEE is approximately:
Show answer & explanation
Correct answer: D - About 84.6 percent
10 free, exam-style Certified Maintenance and Reliability Professional (CMRP) practice questions with answers and explanations. No signup required. Work through them below, then take the full free CMRP practice test to study every exam domain.
A line operates with Availability 90%, Performance 95%, Quality 99%. The OEE is approximately:
Correct answer: D - About 84.6 percent
According to Nowlan & Heap, what percentage of components show age-related (A+B+C) failure patterns?
Correct answer: B - About 11 percent
The FIRST question in the RCM evaluation per SAE JA1011 addresses:
Correct answer: C - Functions and performance
A vibration program detects potential failure 60 days before functional failure. The MAXIMUM appropriate inspection interval is:
Correct answer: D - 30 days
An FMEA shows Severity=10, Occurrence=2, Detection=1, RPN=20. Action should typically be:
Correct answer: B - Taken because S is 10
A pump LCC analysis shows acquisition $80K, operating $150K, maintenance $90K, salvage $20K. What is the LCC?
Correct answer: B - $300,000 net cost
In a RACI matrix, how many people can be 'Accountable' for a single task?
Correct answer: A - Exactly one person
A 90-day PM is due January 30. Per the ±10% rule, the latest compliant date is approximately:
Correct answer: C - About February 8
A facility has annual demand of 1,000 units, order cost of $50, and holding cost of $10/unit/year. The EOQ is approximately:
Correct answer: A - About 100 units
A wrench time study finds technicians at 28%. This is characteristic of:
Correct answer: C - A reactive operation
Practice hundreds more CMRP questions with instant scoring, weak-area drills, and full exam simulations.